This Week - July 19th to July 23rd

• The milling, prep, and pouring of concrete in the northbound slow lane from Comer Street to Rose Street took place this week. The pour should be completed by Wednesday evening. This marks an important milestone, the completion of the concrete portion of the project.
• The replacement of broken curb & gutter, and sidewalk continues this week. This is ongoing, but most sections have been completed.
• Various infrastructure components are being prepared for paving. This includes things like manholes and water valves, which must be adjusted and ready for when the pavers come through.

Next Week - July 26th to 30th

• Depending if all preparation is complete, the reconstruction of the southernmost part of Mackenzie near Highway 20 is scheduled for next week. This includes filling in the ditches and widening for the bike/pedestrian path.
• Paving preparation, which is ongoing, will continue this week, as will the repair of curb and gutter.