Courtesy of the City of Williams Lake:
The installation of new storm water works has continued this week. Next week’s work schedule includes the installation of a drain system in the drainage ditch on the south side and the continuation of road sub-excavation from Hodgson Road to the Pinnacle Pellet area.
The public is reminded that the portion of South Lakeside Drive between the Cariboo Adventist Academy and Hodgson Road is a construction area, and rough patches of road are to be expected. The contractor is regularly working on grading and repairing rough areas, but patience is requested because the high volume of traffic causes road condition to deteriorate quickly. Motorists are also reminded to obey the posted 30 km/h speed limit. Traffic flow will be single-lane alternating.
South Lakeside Drive will be repaved from Hodgson Road to the Cariboo Adventist Academy, the merge lane from Hodgson Road will be extended to Pioneer Drive, and a pedestrian/bike lane will be added from Hodgson Road to the Cariboo Adventist Academy. Work on the project is expected to continue through September.
No comments:
Post a Comment