I'm glad to see the City of Williams Lake resume its' weekly update on the Mackenzie Avenue Rehab Project, after a 2 week break.
Work Currently Underway:
• Paving is currently underway in the area north of Comer Street, known as Section D. The first two asphalt lifts on the southbound lane are underway and traffic is being moved onto the new mat as soon as possible.
• Brief interruptions to driveway access may be necessary for businesses along the river valley side of Mackenzie. When paving of the top lift begins, temporary closures of side streets in this area may be necessary.
• Milling is underway in the north section of Mackenzie near the energy plant, in preparation for paving. The Ball Pit on Soda Creek Road is currently receiving all milling material.
• Drainage improvements have begun between Highway 97 and 20, in the Beaver Valley Feeds area. This will include installing pipe and manholes to capture runoff, eliminating the ditches along the north side of the street.
• Improvements at the intersection of Oliver Street and Mackenzie are now wrapping up.