Courtesy of the City of Williams Lake:
The installation of new stormwater works continued this week on South Lakeside Drive, and will continue next week. Work scheduled to be undertaken next week includes the stripping of topsoil on the north side of the road, and the installation of a fire hydrant.
Traffic will continue to be single lane alternating with delays. Traffic control has been enhanced to allow for better traffic flow. The public is asked to be patient when driving in the area of South Lakeside Drive, and to pay close attention to traffic control personnel.
South Lakeside Drive will be repaved from Hodgson Road to the Cariboo Adventist Academy, the merge lane from Hodgson Road will be extended to Pioneer Drive, and a pedestrian/bike lane will be added from Hodgson Road to the Cariboo Adventist Academy. Work on the project is expected to continue through September.
No comments:
Post a Comment