Work Currently Underway
• Paving of the top lift for the main part of the street will be complete by Wednesday. This marks the end of the major component of the Mackenzie Avenue project.
• Many streets that connect to Mackenzie Avenue require tie-in paving, which is currently underway.
• The final grading for the mixed-use path should wrap up by Wednesday, September 29, at which time it will be prepared for paving. Fine tuning of the grade was required here, which pushed the grading completion back.
• The application of centerline and markings along Mackenzie will begin Monday, October 4.
• It is expected that the parking area of the Community Arts Centre will be paved Thursday, September 30.
-