Courtesy of the City of Quesnel:

Crews have installed the storm main in Phase I of the project. Sidewalks and street lights are being removed from Phase I. The contractor is ensuring access will be given to businesses as soon as sidewalks are removed.  Crews made a connection of the new water main to the Carson Avenue water main. They also eliminated a section of the old water main at the intersection of Reid Street and Carson Avenue.  This week crews will be focusing on water connections to buildings in Phase I and water main connection on Barlow.