Courtesy of the City of Williams Lake:
Installation of curb and gutter on the east half of the project was performed this week, as well as some storm and waterworks on the west half (near 4th Avenue).
Next week, water and sewer line installation will continue on the west half, and into the intersection with 4th Avenue. Motorists are advised that there will be interruptions and closures at this intersection.
No comments:
Post a Comment