Last week on Oliver Street, water service connections were replaced between 2nd and 1st Avenues and irrigation was installed to the islands between 2nd and 1st Avenues.
Work recommenced Sunday, May 29 with the replacement of the main water distribution line at the intersection of 1st Avenue and Oliver Street.
Works are expected to last another three weeks, and there will be intermittent periods of traffic disruption. Work is anticipated to be performed from Sunday during the day and Monday to Thursday starting at 7:00pm. In an effort to perform the work while keeping the downtown open and accessible, traffic and street parking on Oliver Street will be limited during the evening hours after 7:00pm while contractors are at work. While steps will be taken to mitigate disruption, schedules and traffic restrictions may change if circumstances require. The public is asked to exercise caution in the area of construction and to obey signs and the instructions of flagging personnel.
For more information please contact:
Joe Engelberts - Manager of Water/Waste
Phone: 250 392-1785
Email: jengelberts@williamslake.ca
No comments:
Post a Comment