Last week on Oliver Street, irrigation was installed to the remaining planters on the street, and some water services between 1st Avenue and Mackenzie Avenue were completed. There were some delays due to weather.
Work scheduled to be started next week includes more water services at Oliver Street and Mackenzie Avenue, and more water services work, beginning at 3rd Avenue and Oliver Street and moving east. These works include water service saddle replacement, water main valve replacement and replacement of several metres of water mains.
Works are expected to last several more weeks, and there will be intermittent periods of traffic disruption. Work is anticipated to be performed on Sundays during the day and Monday to Thursday starting at 7:00pm. In an effort to perform the work while keeping the downtown open and accessible, traffic and street parking on Oliver Street will be limited during the evening hours after 7:00pm while contractors are at work. While steps will be taken to mitigate disruption, schedules and traffic restrictions may change if circumstances require. The public is asked to exercise caution in the area
For more info - contact Joe Engelberts (Manager of Water/Waste) at 250-392-1785 or jengelberts@williamslake.ca
No comments:
Post a Comment