Reid St Revitalization Project - August 21st update

Courtesy of the City of Quesnel:


Crews completed all of the electrical in phase II and are finishing small electrical jobs in Phase I. All Silva Cells in both phases have been installed. Phase II catch basins have been installed and crews are now prepping for curb installation. The road way is being prepped for paving. Please remember this is an active construction site and follow all signage and direction from the crew.
Take a look at our parking map to see free public parking options. http://bit.ly/2HZMQ06